Geohazard Engineering

Mountain Road — Cyclone Gabrielle Repair

9 slip sites, 159 micropiles, 527 soil nails, 210 m³ shotcrete. Waitākere Ranges.

Location
Waitākere Ranges, Auckland
Customer
Ventia
Designer
GSI
Timeline
Late 2023 — Early 2025
Scope
9 sites — micropiles, soil nails, erosion control

Design

Nine Sites, One Programme, GSI as Designer

Cyclone Gabrielle in February 2023 generated catastrophic slope failures across Mountain Road in the Waitākere Ranges — one of Auckland's key road corridors through the foothills — affecting nine separate sites along the route. GSI was engaged by Ventia as both designer and contractor — a design-build model that allowed the engineering team to adapt solutions in real time as ground conditions varied across the nine sites.

Each site had its own unique design challenges — weak soil, fractured rock, and steep inclines — requiring individual geotechnical investigation and solution. Multiple crews had to work simultaneously within a narrow road corridor, coordinating with civil works and operating under strict environmental rules to protect the area from Kauri Dieback. The solution mix combined high-capacity micropiles, soil nails, shotcrete, and erosion control matting matched to each site's failure mechanism.

Build

159 Micropiles. 527 Soil Nails. 89 Load Tests.

GSI deployed multiple crews simultaneously across the nine sites, adapting drilling techniques to suit the specific slope and access constraints at each location.

Across the nine sites, GSI installed 159 micropiles and 527 soil nails, applied 210 m³ of shotcrete, placed over 2,000 m² of erosion control matting, and poured 253 m³ of no-fines concrete. A total of 89 load tests were completed and provided to Ventia as part of the project QA record — a level of documentation rarely achieved on multi-site emergency repair programmes.

Deliver

Mountain Road Restored Across All Nine Sites

GSI's staged remediation programme restored stability and resilience to all nine slopes along Mountain Road. The design-and-build approach allowed the team to deliver complex geotechnical solutions safely and efficiently despite the access constraints, environmental requirements, and variable ground conditions. Full road access was restored and long-term performance improved.

As both designer and contractor, GSI's single-team model delivered a faster and more integrated response than would have been possible through separate design and construction contracts. Full QA documentation including load test records was provided to Ventia on project completion. Mountain Road is a demonstration of what integrated design-build slip repair looks like at scale — nine sites, one contract, one team.

159
Micropiles Installed
527
Soil Nails Installed
9 Sites
Fully Restored

FREQUENTLY ASKED QUESTIONS

Get in Touch

Facing a Similar
Problem?

GSI has responded to slope failures and emergency geohazard events across New Zealand. If you're dealing with a similar challenge, call us — we move fast.

Discuss Your Project

How Can We Help?

No obligation. One of our engineers will be in touch within 24 hours.