Geohazard Engineering

Lone Kauri & Karekare Roads

8 slip sites, West Auckland — 2,647 m soil nails, 881 m² shotcrete. Cyclone Gabrielle repair.

Location
Karekare & Lone Kauri Road, West Auckland
Customer
Fulton Hogan / Auckland Transport
Designer
Andy O'Sullivan
Timeline
October 2023 — January 2025
Scope
Soil nails, shotcrete, permeable concrete build-out

Design

Eight Sites, One Integrated Programme

Cyclone Gabrielle in February 2023 caused widespread slope failures across West Auckland's road network. Lone Kauri and Karekare Roads — critical access routes into the Waitākere Ranges — suffered eight separate slip sites requiring immediate remediation to restore full two-way access for residents and emergency services.

GSI was engaged by Fulton Hogan and Auckland Transport to design and construct the repairs across all eight sites under a single integrated programme. Working with Andy O'Sullivan Geotechnical Engineering, GSI delivered designed solutions for each site involving the installation of spider anchors, rock bolts, soil nails, and flexible mesh — matched to the geology and failure mechanism at each location.

Build

2,647 Lineal Metres of Soil Nails

Works were sequenced across all eight sites simultaneously, with GSI crews cycling between locations to maintain programme momentum. Across the full programme, 2,647 lineal metres of soil nails were installed, 881 m² of shotcrete facing applied, and 372 m² of flexible mesh facing placed. Drainage upgrades, guardrail installation, and full road reinstatement were completed at each site. The tight access constraints of the narrow road corridor through the Waitākere Ranges required continuous traffic management and careful sequencing to maintain resident access throughout construction.

Deliver

Critical Access Restored to the Waitākere Ranges

All eight slip sites were successfully stabilised and reinstated within the programme period, restoring full two-way vehicle access on both Lone Kauri and Karekare Roads. The works were completed to Auckland Transport's specifications and client satisfaction — delivering a streamlined, cost-effective solution for the repairs.

The project further cemented GSI's position as the go-to design-and-build geohazard contractor for Fulton Hogan and Auckland Transport — demonstrating the efficiency of managing multi-site remediation programmes under a single integrated contract.

The Lone Kauri and Karekare programme stands as one of the most comprehensive multi-site slip repair projects completed in the Auckland region following Cyclone Gabrielle — demonstrating the capacity to manage a high-volume repair programme efficiently under a single design-and-build contract.

2,647 m
Soil Nails Installed
881 m²
Shotcrete Facing
8 Sites
Fully Restored

FREQUENTLY ASKED QUESTIONS

Get in Touch

Facing a Similar
Problem?

GSI has responded to slope failures and emergency geohazard events across New Zealand. If you're dealing with a similar challenge, call us — we move fast.

Discuss Your Project

How Can We Help?

No obligation. One of our engineers will be in touch within 24 hours.