Kenepuru Substation
Foundation and slab re-levelling by polyurethane resin injection in Porirua, with no excavation or operational downtime.
- Location
- Kenepuru Substation, Kenepuru, Porirua, Wellington
- Service
- Polyurethane (PU) resin injection
- Lift
- Up to 126 mm, controlled and gradual
- Assurance
- PS3 Producer Statement and warranty-backed outcome
Design
Foundation Settlement Driven by Groundwater and Poor Drainage
The Kenepuru Substation had suffered significant foundation settlement. Elevated groundwater and inadequate drainage had raised pore water pressure in the founding soils, reducing effective stress and shear strength. The slab and foundation had settled differentially by up to 126 mm, leaving unsafe floor gradients that affected maintenance access, cracking in the blockwork that let moisture in, and an ongoing risk of further subsidence.
The asset needed re-levelling without excavation, structural disruption or operational downtime. The soils were particularly dense and highly compacted, which limited conventional injection approaches and called for a controlled, engineered solution. GSI began with a site inspection, a site survey and soil analysis, and carried out Dynamic Cone Penetrometer (DCP) testing before treatment. Lift tolerances were defined to provide functionality once the structure was re-levelled.
Build
Gradual Lift Without Touching the Slab
A targeted polyurethane resin injection programme re-levelled the structure and improved the subgrade. Injection was carried out through the service channel foundations, which kept the work clear of the power lines and meant nothing penetrated or disturbed the slab surface.
The expanding resin increased soil density, reduced void ratios and improved load-bearing capacity while allowing precise level correction. Lift was applied gradually to avoid inducing structural stress. Work followed agreed hold points to monitor cabling and transformers, with real-time monitoring of lift and response throughout.
Deliver
Levels Restored. Back in Service Straight Away.
Slab and foundation levels were restored within design tolerances, with no additional structural stress or damage. A controlled lift of up to 126 mm was achieved, and the asset returned to operational condition immediately after injection.
Post-treatment DCP testing confirmed a measurable increase in soil strength across all tested depths, with significant improvement below footing level (0.6 to 1.0 m). Pore pressures were reduced through resin expansion and water displacement. A post-treatment level survey verified the result, and a PS3 Producer Statement was issued confirming compliance. Minor surface movement in the adjacent hardstand was within expected limits, and some localised hairline cracking at the lowest corner did not require slab injection.
FREQUENTLY ASKED QUESTIONS
Related
Get in Touch
Settled Slab or
Critical Asset?
Tell us about your site and one of our engineers will advise on whether polyurethane injection can re-level it without excavation.
Call Us: +64 9 885 6320 →