Geohazard Engineering

Dome Valley — SH1 Landslide

118 rock anchors, Geobrugg TECCO mesh, and rope access installation — State Highway 1 north of Auckland.

Location
SH1, north of Auckland
Main Contractor
Wharehine Contractors Ltd
Designer
GSI / Andy O'Sullivan
Timeline
December 2024 — March 2025
Scope
Dimensioned soil nail system with Geobrugg G65/s TECCO mesh

Design

Accessible Only From Above

An unprecedented weather event in 2023 caused a landslide blocking part of SH1 near Dome Valley, north of Auckland. The failed slope face was inaccessible from the road below and from the hillside above without preparation. Our design team specified a helicopter landing area to be cut into the upper slope — the only viable access point for personnel, plant, and materials.

Three weeks of site preparation preceded the main stabilisation works, including creation of the landing area, temporary rainforest tracks, and a bridge across Hoteo Stream for reliable access during rainfall. The design solution centred on a dimensioned soil nail system using Geobrugg G65/s TECCO mesh — a lightweight, high-tensile mesh system that could be transported and installed entirely via rope access and aerial delivery, without requiring heavy plant on the slope face itself. The Dome Valley project was delivered as a design-build contract, with GSI's in-house engineers developing the solution and the same team constructing it from helicopter-accessed positions above the slope.

Build

Day and Night, Rock Removed by Hand

GSI partnered with Andy O'Sullivan & Associates as designer and Wharehine Contractors as main contractor. The construction programme was phased to maintain minimal lane closures on State Highway 1, one of New Zealand's busiest arterial routes, while complying with Department of Conservation requirements for works within the Sunnybrook Scenic Reserve and engaging with local iwi throughout.

Over 200 m³ of rock material was removed entirely by hand — no mechanical plant was used on the slope face. Crews worked day and night shifts to meet programme. A lightweight pneumatic drill was suspended from the helicopter landing area above to install the rock anchors into the stabilised face, with IRATA-certified rope access operators leading all face work. Dome Valley is one of the most demanding helicopter-access geotechnical projects completed on New Zealand's state highway network.

Deliver

118 Rock Anchors. 790 m² of Mesh. SH1 Reopened.

The completed works delivered 118 installed rock anchors across the face, with 790 m² of Geobrugg TECCO G65/s mesh covering the stabilised slope. The system provides permanent protection against further rock movement and slope failure, with the mesh system designed to intercept and retain any future loose material above the highway corridor.

Works were completed within programme, SH1 traffic impacts were minimised throughout, and the site was left to full DoC and iwi satisfaction. The Dome Valley project is a demonstration of what is achievable through thorough pre-planning and rope access methodology on sites where standard access is simply not possible. GSI NZ provides landslide stabilisation and slope repair services across New Zealand, with specialist capability for remote and inaccessible sites.

118
Rock Anchors Installed
790 m²
Geobrugg TECCO Mesh
ON PROGRAMME
SH1 Reopened

FREQUENTLY ASKED QUESTIONS

Get in Touch

Facing a Similar
Problem?

GSI has responded to slope failures and emergency geohazard events across New Zealand. If you're dealing with a similar challenge, call us — we move fast.

Discuss Your Project

How Can We Help?

No obligation. One of our engineers will be in touch within 24 hours.